Cutting inside live water infrastructure: what asset owners require

Cutting concrete inside operating water infrastructure is its own discipline. The asset keeps supplying customers while you open its walls. Here is what the asset owners require, drawn from work delivered inside a live Sydney Water plant.

The conditions come first

On the Prospect Pre-Treatment Plant works, the conditions were set before any contractor priced a cut: no heavy mechanical plant inside the channel at any time, saw-cut precision openings only with no impact breaking, and a minimum 100 mm standoff from every construction joint so the PVC waterstops stayed intact. Conditions like these are not obstacles to the method. They are the method. A contractor who prices the concrete without pricing the conditions has not understood the job.

Vibration is the quiet deal-breaker

Water retaining structures are sensitive to vibration in ways buildings are not. Cracks mean leaks, and leaks in a live asset mean shutdowns nobody scheduled. Diamond wire and wall sawing are effectively vibration free, which is why they are usually the only cutting methods an asset owner will accept near retained water infrastructure.

Overcut protection has to be physical

Telling an operator to stop the cut at a line is a control. Drilling a stitch core at the cut termination so the wire physically cannot travel past it is a better one. On critical assets, the methodology should make the worst outcome impossible rather than unlikely.

Your water cannot touch their water

Diamond cutting uses water, and cutting water becomes high pH slurry. Inside a drinking water catchment that slurry must be contained at the cut, collected and removed through EPA licensed facilities, with the waste separated by stream. Asset owners will ask for this plan in writing, and they are right to.

What this looks like delivered

The full story of the Prospect works, including the seven panel wall opening and the crane lift sequence, is in our Prospect Pre-Treatment Plant case study. The planning approach behind it is described on our cutting engineering and methodologies page.

Talk to a real personCall now

aboriginal flagsDeconCut acknowledges the Aboriginal and Torres Strait Isander people as Traditional Custodians of the country on which we live and work. We pay our respects to the Traditional Custodians and Elders past, present and future, and honour their connection to the land and ongoing contribution to society.